Notre Dame Reopens to the Public
Five years after the catastrophic fire on April 15, 2019, Notre Dame reopened to the public on December 8, 2024.
Over 2,000 highly skilled artisans worked with donations from 340,000 donors from 150 countries around the world to restore the beloved cathedral in this larger-than-life project.
For previous posts about this project, see Should Notre Dame Get A Makeover? and Notre Dame’s Makeover Creates a Project Management Challenge.
Video Spotlight:
- Get a first glimpse inside the newly restored Notre Dame Cathedral (Nov 29, 2024, TODAY)
- The Resurrection of Notre Dame | 60 Minutes Archive (Nov 29, 2024, 60 Minutes)
This post is based on the CNN article, Notre Dame is back, but not quite as you know her, by Joseph Ataman, November 30, 2024; The Hill article, Timeline: Notre Dame Cathedral’s 5-year rebuild post-fire, by Ashley Soriano, November 30, 2024; the BIMsmith blog post, The Restoration of Notre Dame: Four Years Later, by BIMSmith, April 13, 2023; and the YouTube videos in the Spotlight. Image source: James R. Martin/Shutterstock
Discussion Questions:
1. What was thought to be an initial timeline for the reconstruction, and how did that timeline compare with the ultimate completion date?
Guidance: Two days after the horrific fire saddened the hearts of people around the world in April 2019, President Emmanual Macron vowed to reconstruct the cathedral in five years. The damage, however, was extensive, including a gaping hole in the ceiling left when the lead-covered spire which sat atop the cathedral collapsed. In addition to rebuilding, everything had to be extensively cleaned to remove years of grime that had built up before the fire in addition to all the residue and damage from the fire and the subsequent attempt to put it out.
Some observers estimated a minimum timeline of 15 to 20 years for the extensive reconstruction project for Notre Dame.
Amazingly, the bulk of the work has been completed in just five and a half years.
The original hope was to have it ready to open for the Summer Olympics in Paris. While that deadline was missed, the pace of progress was remarkable none-the-less, particularly considering that a significant portion of the project timeline ran through the pandemic.
As a sidenote, although the cathedral opened to the public on December 8, 2024, some remaining parts of the reconstruction project are expected to stretch into 2026. The apse and the sacristy are slated to be done by the end of 2025. Six new stained glass windows are undergoing a competitive design update and are due to be installed by the end of 2026. The original stained glass windows from the south side of the nave will be moved to a museum.
Large projects, such as this one, which has so far cost approximately 700 million euros, often experience numerous delays and fall behind schedule. Such projects also tend to significantly exceed initial cost estimates. However, in this case, despite the scale and unique nature of the project, it has come in fairly close to initial cost estimates and all things considered, very close to the desired completion date.
While missing the 2024 Summer Olympics deadline meant that visitors to those events were not able to experience the restored cathedral, the scale of the restoration was massive and will ensure the health of the structure well into the future.
2. What was unique about the nature of the tasks and materials for this project as compared to other construction projects? How did modern technology play a role in this process?
Guidance: An initial decision had to be made about whether to restore Notre Dame to its previous state or modernize it. Considerable debate took place until it was ultimately determined that the cathedral should be returned to its original design, including the original design of the collapsed spire that had been added in 1859.
Interestingly, cutting edge architectural technology played a key role in ensuring that every detail was as historically accurate as possible. Prior to the fire, a detailed three-dimensional digital model (3D BIM building information model) had fortuitously been developed by Autodesk, which generously shared the plans with those heading the restoration project.
As far as materials were concerned, everything possible was done to source the same materials that were used in the original construction.
Some of the oldest beams had come from a tree that was felled in 1156, and most of the beams were made prior to 1226. France currently has the largest supply of mature oaks in the world, and the restored ceiling is comprised of about 1200 oak logs that came from the same former royal woods that provided the beams for the initial construction. In addition to needing to source the materials from the west of France, they had to be transported to northeastern France to be carefully hewn into roofbeams and then sent down the Seine to get back to the cathedral.
Stone, lead and other materials also had to be sourced to provide the same kinds of inputs that were originally used.
Over 2,000 skilled artisans, in addition to modern construction companies with the latest equipment, worked together to blend the look of the old with the equipment, technology, and safety of the new.
3. What may have been some of the major tasks in the work breakdown structure (WBS) for this project?
Guidance: From written reports about the project, it appears that the following may have been some of the major tasks at the top of the work breakdown structure hierarchy:
1. Securing the safety of the cathedral (April 2019-August 2021)
2. Cleaning and repairing parts of the cathedral that survived the fire:
> Pipe organ cleaning and restoration (beginning in August 2020)
> Stained glass window cleaning and restoration (beginning in Spring 2022)
> Repair of bells and creation of new replacement bells (completed November 7, 2024)
3. Wooden spire construction and attachment (completed in February 2024)
4. Roof and truss reconstruction (completed March 8, 2024)